Alexander Richter 2 Dec 2016

KS Orka is now rigging up the second drilling rig on site for the Sorik Marapi geothermal project in Indonesia.

The drilling team to drill for the Sorik Marapi geothermal project in Indonesia has arrived on site.

In a post, KS Orka reports hat the drilling rig of the company is now being rigged up on Pad E on the project site.

The KS Drilling rig is now being rigged up on pad E in Sorik Marapi Indonesia.  Dati Parker are just about to finish their first well on pad A.

The Sorik Merapi project is one of the largest geothermal greenfield projects in Indonesia, with an expected development size of 240 MW. KS ORKA is the 95% owner and developer of the project. The company has two drilling rigs on site.

Source: KS Orka