Nevis geothermal project prepares for arrival of drilling rig

Nevis geothermal project prepares for arrival of drilling rig Preparing of the drilling pad, Nevis, Caribbean (Nevis Clean Power Nevis)
Alexander Richter 7 Sep 2017

The developer of the Nevis Geothermal Project in the Caribbean has announced preparations have been concluded for the arrival of the drilling rig for the project.

With limited news over the past few months, the developer of the geothermal project on Nevis in the Caribbean has now announced that it was able to clear the site for the drilling rig a mere  four days prior to the arrival of Hurricane Irma,

With the completion of the preparation, the Nevis Geothermal project has reached a milestone for the project that is slated to become the first Binary ORC Geothermal power plant on the Caribbean Islands.

The drilling rig to start drilling is scheduled to arrive on the island on October 4, 2017 with drilling to commence thereafter.

Source: Clean Power Nevis